Webb Dock West, Automotive Terminal

Project Information

Calendar Icon

Completion Date: March 2015 - Feb 2016

Location Icon

Location:

Client Icon

Client: Port of Melbourne Corporation

Sector Icon

Sector : Commercial/Industrial

Overview of Project

A 31,000m² post-tensioned hardstand project was completed for the Port of Melbourne Corporation by Leightons (CPB). This involved 8,000m³ of VicRoads specification concrete. The average pour size was 2,600m², with approximately 700m³ poured per pour. To mitigate the risk of cold joints in the post-tensioned slabs (due to the large concrete volumes and pour area), all work commenced at 1:00 am, ensuring prompt concrete delivery and preserving slab integrity. The project was completed within 12 weeks by the expert team at SpeedPro civil.

Project Info

  • Completion Date: 2025-02-21
  • Location: Melbourne
  • Client: Port of Melbourne Corporation
  • Sector: Commercial/Industrial
  • Category: Commercial / Industrial