Somerton Project

Project Information

Completion Date icon

Completion Date:

Location icon

Location: Melbourne Intermodal Terminal, Somerton

Client icon

Client:

Sector icon

Sector : Commercial/Industrial

Overview of Project

Speedpro Civil played a key role in delivering major concrete works for the Melbourne Intermodal Terminal in Somerton, showcasing our capability in managing high-volume concrete pours, complex reinforcement, and critical scheduling.

Scope of Works:

  • Successfully poured 84 post-tensioned base slabs, placing over 67,497 m³ of concrete, with an average slab size of 2,000 m² at 340mm depth.
  • Completed extensive night shift operations, with pour placements commencing as early as 1:00 AM, ensuring project timelines were met with minimal disruption.
  • Delivered complex rail-mounted gantry beams, placing a further 6,779.2 m³ of concrete to support critical infrastructure.
  • Constructed an 8 megalitre Stormwater Detention Tank, which consisted of base slab construction, off-form concrete walls and hollow core plank stitching screeds; the project included the installation of 93.5 tonnes of reinforcement and placement of 1,117.2 m³ of concrete.

Speedpro Civil’s expertise in large-scale concrete placement, complex buildability problem solving, and our commitment to precision, reliability, and innovation were key to the successful delivery of this significant infrastructure project.

Project Info

  • Completion Date:
  • Location:
  • Client:
  • Sector:
  • Category: Commercial / Industrial