Mentone LXRP

Project Information

Calendar Icon

Completion Date: Dec 2019–Sept 2020

Location Icon

Location:

Client Icon

Client: Southern Project Alliance

Sector Icon

Sector : Rail/Road and Infrastructure

Overview of Project

A significant concrete construction project was completed for the Southern Project Alliance. The scope encompassed a 4,800m² FRP package for rail tanking slabs, the Balcombe Road bridge and abutments, and a heritage deck slab station concourse. Over 4,000m³ of concrete and 1,100 tonnes of reinforcement were installed within a three-week timeframe. Additionally, 1,300 linear meters of capping beams and 700 linear meters of in situ walls and upstands were excavated, formed, reinforced, and poured.

Project Info

  • Completion Date: 2025-02-21
  • Location: Melbourne
  • Client: Southern Project Alliance
  • Sector: Rail/Road and Infrastructure
  • Category: Road, Rail & Infrastructure