Ctd 9 Level Crossing Removal Super Structure

Project Information

Completion Date icon

Completion Date: Dec 2016 - Feb 2017

Location icon

Location:

Client icon

Client: Level Crossing Removal Authority

Sector icon

Sector: Rail/Road and Infrastructure

Overview of Project

SpeedPro Civil’s work involved unloading and installing 1,375 precast derailment kerb panels on the elevated rail corridor and fixing approximately 1,150 tonnes of reinforcement, including electrical continuity welding. 15,877 ferrules were cast in to bond the rail plinths to the deck. SpeedPro Civil also placed and finished 10,227m² of suspended concrete rail corridor slabs, formed, reinforced, and poured 74 Super T diaphragms, and formed and installed 214 drainage cover plates.

Given the project’s tight deadlines, our team implemented multiple work fronts and utilised crews working day and night, up to seven days a week, during occupation periods. Through proactive planning, SpeedPro Civil successfully met all productivity requirements and delivered a quality product within the allocated timeframe.

Project Info

  • Completion Date: 2025-02-21
  • Location: Melbourne
  • Client: Level Crossing Removal Authority
  • Sector: Rail/Road and Infrastructure
  • Category: Road, Rail & Infrastructure
Scroll to Top