HCMTP Train Maintenance Facility – Foundations

Project Information

Completion Date icon

Completion Date: June 2017 – Sept 2017

Location icon

Location:

Client icon

Client: Metro Trains

Sector icon

Sector : Rail/Road and Infrastructure

Overview of Project

This Downer’s contract included excavating, forming, reinforcing, and pouring 178 pad footings. Some of these footings measured up to 10m x 3m x 0.8m and required two sets of HD bolts, all installed within a tight tolerance of +/- 5mm. To expedite the process, given the number and size of the footings, SpeedPro civil prefabricated the reinforcement cages, placing the HD bolt sets loosely inside for on-site setting. This approach significantly reduced on-site steel fixing time.