Project Information
Completion Date: May 2019 - Nov 2019
Location: Webb Dock (Assumed to be Melbourne, Victoria, due to context)
Client: CIVILEX
Sector : Commercial/Industrial
Overview of Project
SpeedPro civil has completed six of seven concrete pours at Toll Group’s shipping terminal at Webb Dock. The project involves 20,000m² of post-tensioned slab on groundworks, totalling over 5,500m³ of concrete. These slabs, a design change from conventional asphalt, were chosen for increased durability. The sixth pour, completed recently, covered 3,263m² and used 876m³ of concrete, all poured within a 4mm tolerance. Slab preparation is underway for the seventh and largest pour (3,427m²), scheduled for completion in a week and a half.
Project Info
- Completion Date:
- Location: Webb Dock (Assumed to be Melbourne, Victoria, due to context)
- Client: CIVILEX
- Sector: Commercial/Industrial
- Category: Commercial / Industrial